Environmental Study and Public Participation for the Rojana Power 3 (SPP3) Combined Cycle Power Plant Development, Phra Nakhon Si Ayutthaya Province

Client : Rojana Power Co., Ltd. 

The Rojana Power 3 (SPP3) Combined Cycle Power Plant Project is situated in Rojana Industrial Park 3 over a total area of 27 rai. The aim was to further national energy security, particularly in Phra Nakhon Si Ayutthaya Province. Natural gas is carried via a 12-inch transmission pipeline. The plant will consume water from Rojana Industrial Park. The water for initial treatment will be reused before being released to a wastewater treatment plant and external water resources respectively. With generation capacity of about 90 MW, the plant exports power to the Electricity Generating Authority of Thailand and retains some power for internal consumption.

TEAM GROUP was entrusted with general analysis, preparation of an EIA report, survey and monitoring of environmental quality before project development, and a public hearing activity.



 